Overview  |  Markets  |  Showcase Projects  |  Clients

Showcase Projects

Hospitals
Johns Hopkins BRB
Johns Hopkins CRB

Laboratories/ R&D
Advanced Chemistry Laboratory
The Institute for Genomic Research
Human Genome Sciences
Walter Reed Army Institute of Research
The Celera Genomics Corporation
Army Physical Sciences Facility
University of Maryland Center for Advanced Research in Biotechnology

Data Centers
AOL
Verio
Digex

Office Buildings
Montgomery Business Park
Baltimore City Police Headquarters


Conference Centers
Washington D.C.
Baltimore

Hotels
Mandarin Oriental
Embassy Suites Hotel

Theatre
Frances Merrick Performing Arts Theatre (Hippodrome)

Sports/Recreation
M&T Bank Stadium
Oriole Park at Camden Yards
University of Maryland Comcast Arena

Wastewater and Water Treatment
Back River W.W.T.P.
Patapsco W.W.T.P.
Hillen Pumping Station
Ashburton Filtration Plant

Correctional Facilities
Baltimore City Juvenile Justice Center

Airports
Dulles International
BWI A/B Expansion

Showcase Projects
Baltimore City Police Headquarters

Client/Owner
The City of Baltimore

Location
Baltimore, Maryland

Architect
Hellmuth, Obata & Kassabaum

Engineer
Allen & Shariff

General Contractor
The Poole and Kent Corporation

Contract Amount
$34,778,411

The Project
To meet the expanding needs of the Baltimore City Police Department, a new 95,778 sq. ft. Annex was added to the existing headquarters building, and the existing building was fully renovated with new architectural finishes, and mechanical systems. Due to the interconnection of the buildings, and the antiquated original building the Annex addition was connecting to, it was necessary to perform asbestos abatement during construction. The new Annex building provides 321,467 square feet of office space, and 94,504 square feet for parking.

PK Role
Poole and Kent served dual roles on this project as both the General Contractor and Mechanical Contractor. The scope of work for the new Annex building involved architectural finishes, mechanical (HVAC, Plumbing and Piping) and electrical services. The existing building was gutted of all architectural finishes, and mechanical systems. Asbestos removal was necessary in the existing building. New areas were constructed in the existing building including forensic and photographic laboratories.

Highlights/Challenges
There was major scope change during the demolition of the 8th floor of the existing building requiring the demolition to continue under asbestos abatement conditions. This prolonged the project duration and required re-phasing of the construction plan. Poole and Kent led a re-sequenced construction to begin at the top of the building in lieu of starting construction at the bottom of the building. The re-sequencing of construction activities enabled construction to continue without interruption from the necessary abatement processes.

Despite the major change in construction sequence, a first-class facility was delivered to the City of Baltimore, and all work was performed within the modified construction schedule.